Ian
J. Burgess, P. Eng.
Senior
Electrical Engineer

Bachelor of Science Degree
in Electrical Engineering, University of New Brunswick, 1975
Master of Science Degree
in Electrical Engineering, University of New Brunswick, 1978
Registered Professional Engineer
in the Province of New Brunswick
Member of the Institute of
Electrical and Electronic Engineers (IEEE)
Member of the International
Society for Measurement and Control (ISA)
Twenty-eight years experience
in electrical engineering.
WORK EXPERIENCE:
June 1997 to Present - E & I Engineering
Ltd.
-
Co-founder of E&I Engineering.
-
Irving Personal Care Limited:
Project Engineer responsible for the Electrical and Instrumentation design for a
greenfield $65 million dollar diaper manufacturing facility. This involved the
complete design for the power distribution, motor control, instrumentation,
control system design and building services. Also responsible for the
construction supervision and commissioning and startup of the plant.
-
Coleson Power Group: Project
Engineer in the Controls Group responsible for the cutover design of the
existing control system to the new DCS. This involved a detailed review of the
exiting wiring and drawings and the subsequent design of the new system that
would allow a cutover of each of the three units while the other two units
remained on-line. Also involved in other various control aspects of the project
including DCS selection, PLC integration as well as being responsible for the
preliminary engineering cost estimate for the controls portion of the project.
-
Noranda - Brunswick Mine,
Paste Backfill Project: Project Engineer responsible for the coordination
of the Electrical and Instrumentation portion of this $23 million dollar
project on behalf of the owner. This involved supervision and direction
to the consulting engineers as well as coordination with plant staff. Also
responsible for the construction supervision and commissioning of the plant.
In addition, responsible for the coordination of the control system design
and implementation of a hybrid control system using a Fisher Provox DCS
and an Allen-Bradley PLC.
-
Noranda - Brunswick Mine,
Ag Mill Project: Commissioning Engineer responsible for commissioning of a
$25 million dollar Ag Mill plant. Coordinated contractor’s work and was
responsible for any design changes. Supervised commissioning of electrical and
instrumentation systems with plant staff. Also worked closely with
manufacturer’s representatives to tie their systems into the plant electrical
and control systems.
- Noranda - Brunswick Mine,
Miscellaneous Projects: Design and Commissioning Engineer for the
following projects:
- Controls Upgrade for the 6MW Gas Turbine
Generator. This involved conversion of relay controls to a PLC based
control system. Also carried out all power cabling and protective relaying
modifications and checkout.
- 6000KVAR Capacitor
Bank Installation. This project
involved power system design,
installation supervision and commissioning of a de-tuned 13.8kV, 6000 kVAR
capacitor bank.
-
Underground Power System Upgrade Project.
This project involved power system design, installation supervision and
commissioning of a $970K power system upgrade for the underground power
distribution system. Project management and cost controls were also
provided.
-
Irving Tissue Company – TM1
Electrical System Upgrade: Design Engineer responsible for the design
of the upgrade of the No. 1 Tissue Machine electrical system from 6.9kV
to 13.8kV. This project involved construction of a new electrical substation,
new MCC’s, cable tray system and controls. A new DCS control system will
be installed as all the existing motors will be converted to DCS control.
This work will be carried out in an operating plant during operation of
the mill and during the monthly shutdown days. Also responsible for carrying
out coordination, harmonic and power factor studies.
-
Stone Container (Canada)
Ltd. – Design Engineer responsible for design of the Electrical and
Instrumentation for the installation of a new lube system for Paper Machine
No. 6. This involved installation of a new MCC, power distribution and control
cabling. Coordinated control philosophy with plant staff and wrote PLC program
for motor control portion of project
Also commissioned and
assisted in the startup the system.
-
Noranda inc. - Heath Steele Mines:
Design
Engineer and commissioning Engineer responsible for the following projects:
- B-Mine Pump Station.
This project involved the
installation of a new pump station. Design responsibilities included power
system distribution, control and instrumentation.
-
Pioneer Chemicals Canada Inc.:
Design engineer
responsible for the electrical and instrumentation design for the following
project:
- Spill Prevention Project: This
project involved installation of instrumentation and a PLC system to prevent
spills in caustic soda delivery system.
- MCC Upgrade Project: This
field-mounted starters to a
new MCC Room based system. As part of the project a new PLC system was installed
to control the motors.
July 1, 1985 to May 30, 1997 - Neill
and Gunter Limited
-
Electrical Engineering Department Manager
from September/86 to September/96
-
Design Engineer for many small and several
large projects throughout the 12 years at Neill and Gunter. These projects
mainly involved power distribution and control in an industrial environment.
Some of the larger projects are as follows:
-
SSP Project – March/94 to October/96
- Design Engineer for the commissioning, start-up and operation of
a novel plasma-based waste incineration pilot plant in Singapore. Involved
in the power supply design and implementation as well as all aspects of
power distribution, control and instrumentation.
-
N. B. Power Belledune Generating Station
Project – January/91 to March/94 - Design Engineer for the design and
commissioning of the plant metering, station service transfer, generator
protection and unit synchronising systems for a 450MW coal fired power-generating
station.
-
Presswood Pallet Plant - ACUMA Presswood
Pallets Inc. - Project Engineer responsible for the design of the power,
control, and lighting circuits for a 45,000 square foot facility. This
plant included a Data Highway with 9 Allen-Bradley PLC 5's and a central
Data Monitoring PC. Also supervised the commissioning and start-up of the
electrical and control portions of the plant.
-
Winder Rebuild Project - Rothesay Paper
Ltd. - Project Engineer responsible for the design of power and control
circuits required for the installation of new drives, programmable controllers
and complete new power and control wiring for two paper machine winders.
Site services during shutdown and commissioning were also provided. Project
Manager for this job overseeing the work of the mechanical and civil portions
of this job.
-
Woodroom Project - Rothesay Paper Ltd.
- Project Engineer responsible for the conversion of the woodroom from
relay and pneumatic controls to a completely digital control scheme using
an Allen-Bradley 2/30 programmable controller and several colour graphics
consoles. Also responsible for supervising the commissioning of this project
for the client.
-
Power Systems Engineer carrying out
the following power system studies:
-
Design of overhead power distribution
lines.
-
Power system study with regard to plant
expansion.
-
Power factor studies.
-
Fault and protection co-ordination studies.
-
Substation ground grid design.
-
Ground potential rise study.
-
Harmonic analysis.
December 1, 1983 to June 30, 1985 Allen-Bradley Canada
Ltd.
-
Sales Engineer for a major control equipment
supplier. In this role became very familiar with motor control and PLC
equipment. As well, became familiar with the many industries in the province
of New Brunswick.
July 1,1981 to November 30, 1983 Fenco Shawinigan
Maritimes Limited
-
Design Engineer involved mainly in medium
voltage power distribution system design for industrial plants. Also carried
out several fault and protection coordination studies for customers such
as Brunswick Mining and Smelting, DND Halifax, Texaco Oil Refinery and
Consolidated Bathurst.
July 1, 1977 to June 30, 1981 New Brunswick Electric
Power Commission
-
Protection Relay Engineer: Worked in the
Relay Group responsible for the setting of all the protection relays for
the transmission and generation systems for the utility. Worked in this
role for approximately 2 years.
-
System Performance Engineer: Worked in
the system Performance Group responsible for testing miscellaneous control
systems in generating stations and switchyards. This included station services
transfer schemes, unit synchronization schemes and fault recorder systems.
|